Ineco will continue working until the end of 2020 on the final stage of the renovation of the 377.8 km railway line (in addition to the branch between Samsun and Gelemen, which is just over 10 km long) that links the cities of Samsun, on the Black Sea coast, and Kalin, in the centre of the country, where it connects to the Ankara-Sivas line. After almost five years, the work is now in its final stages. In 2019, construction work was completed on the entire line, except for the Gelemen branch. Once completed, the fault notification period can begin, with an expected duration of 12 months, followed by the acceptance and commissioning of the line. Ineco’s work will last until December 2020.