{"id":3636,"date":"2019-08-29T15:05:00","date_gmt":"2019-08-29T13:05:00","guid":{"rendered":"https:\/\/www.revistaitransporte.com\/?p=3636"},"modified":"2019-09-02T08:18:30","modified_gmt":"2019-09-02T06:18:30","slug":"the-ave-conquers-granada","status":"publish","type":"post","link":"https:\/\/www.revistaitransporte.com\/the-ave-conquers-granada\/","title":{"rendered":"The AVE conquers Granada"},"content":{"rendered":"

Pre-validation tests on the line between Antequera and Granada ended on 20 December 2018, when traffic control was transferred to Adif Alta Velocidad. The infrastructure manager then gave the green light for the start of a period of internal ERTMS traffic testing between Antequera and Granada, prior to reliability and training processes. Once this phase is complete, the high-speed AVE connection between the capital of Spain and the city that is home to the Alhambra will be a reality.<\/p>\n

The 114\u00a0kilometres of line between Antequera and Granada and its direct connection to M\u00e1laga via the Gobantes Junction have been built predominantly in standard gauge, 33% double-track and the rest single track electrified at 25\u00a0kV with a top speed of 300\u00a0km\/h. The exception is 26.3\u00a0kilometres of mixed-gauge line consisting of three rails where the line passes through Loja and at the entry into Granada. With the commissioning of the new line, Granada is now finally connected to the rest of the Spanish high-speed network through the C\u00f3rdoba-M\u00e1laga line.<\/p>\n

Ineco has participated in the development and construction of this line since its beginnings, carrying out various projects that include consulting and technical assistance for the environmental management of the entire final stretch in Andalusia; platform construction management, project and construction management of the Antequera, Loja and Granada high-speed stations; clearance studies and adaptation of the Loja tunnels; consulting and technical assistance for the construction management of track assembly, and power, signalling and communications facilities along the entire line.<\/p>\n